COOPERATION BETWEEN SUE "DUSHANBEVODOKANAL" AND INTERNATIONAL PARTNERS

SUE "Dushanbevodokanal" (DVK) is carrying out a large-scale and consistent modernization of the entire water supply and sanitation system of the capital of the Republic of Tajikistan. This work is conducted as part of the implementation of state programs and relies on a long-term strategic partnership with leading international financial institutions.

Cooperation with key international donors—the Asian Development Bank (ADB) and the World Bank (WB)—has today moved far beyond the traditional attraction of investment loans and grants. It represents a comprehensive, deeply integrated program of institutional and technical transformation for the entire urban water sector. Joint projects are aimed at adapting the city’s life-support systems to high rates of urbanization and the challenges of climate change.

Currently, multi-vector cooperation with international partners is being successfully implemented across three strategic areas:

1. Infrastructure Modernization and Environmental Safety Assurance
Investment infusions from international donors are aimed at the capital renewal and expansion of the enterprise's physical assets, which makes it possible to dramatically increase the reliability of urban infrastructure.

1.1. Reconstruction of Headworks: Projects include the deep modernization of water treatment plants (WTP), first and second-lift pumping stations, and the introduction of modern, safe drinking water disinfection technologies.

1.2. Restoration and Expansion of Networks: Large-scale work is underway to replace worn-out main water pipelines and reconstruct gravity and pressure sewage collectors, which minimizes the risks of accidents and improves the sanitary and ecological situation in the city.

1.3. Loss Management and Network Zoning: A crucial practical step is the division of the urban network into isolated District Metered Areas (DMAs). This allows for continuous monitoring of supply volumes, effective management of hydraulic pressure, and systematic reduction of commercial and technical losses (non-revenue water).

2. Digital Transformation, Automation, and Customer Service Optimization.
Modern management standards require a transition to digital technologies. Joint projects with the ADB and the World Bank provide for end-to-end automation of all production and sales chains of SUE "DVK."

2.1. Introduction of SCADA Systems: A unified intelligent Supervisory Control and Data Acquisition (SCADA) system is being created, which allows for real-time monitoring of pumping unit operations, reservoirs, and key metering nodes.

2.2. Development of Commercial Metering: A phased transition to "smart" water meters (smart meters) with remote reading transmission capabilities is being implemented, ensuring absolute transparency in calculations with consumers.

2.3. Modernization of IT Infrastructure and Call Center: A complete transformation of the enterprise's contact center is underway, shifting from manual processes to modern digital platforms. The integration of the Call Center with Geographic Information Systems (GIS) and the updated billing system allows for prompt responses to citizen requests, reducing the time required to resolve emergency situations.

3. Institutional Development, Corporate Governance, and Gender Equality.
The sustainability of technical achievements is impossible without the modernization of management approaches. Within the framework of assistance programs, special attention is paid to strengthening the institution of SUE "Dushanbevodokanal" itself as a financially stable enterprise.

3.1. Results-Based Management: International corporate governance standards are being introduced at the enterprise, including a clear system of Key Performance Indicators (KPIs) and the use of Performance-Based Contracts in operational activities.

3.2. Capacity and Expertise Building: Advanced training programs are regularly conducted for engineering, technical, and administrative personnel, including the organization of international study tours to exchange experience with advanced water utilities in foreign countries.

3.3. Implementation of Gender Policy and Inclusivity: One of the priority vectors of cooperation is overcoming gender stereotypes in the municipal sector. Programs to support women's leadership are being developed and implemented, creating equal conditions for the professional and career growth of female specialists in the engineering, IT, and management spheres of DVK.

Main Strategic Goal of the Partnership

The accumulation of advanced international experience and investment is aimed at creating a financially sustainable, high-tech, environmentally responsible, and customer-oriented utility enterprise. SUE "Dushanbevodokanal" strives to guarantee uninterrupted, safe, and economically affordable water supply and sanitation for every resident, state institution, and commercial enterprise of the dynamically developing capital.

ASIAN DEVELOPMENT BANK COOPERATION WITH SUE "DUSHANBEVODOKANAL"

1. Financing Stages. With the objective of improving the water supply situation, providing the capital's residents with reliable access to clean drinking water, and enhancing sanitation conditions, the Dushanbe Water Supply and Sanitation Project has been implemented since 2018 pursuant to grant and loan agreements between the Government of the Republic of Tajikistan and the Asian Development Bank (ADB). The project financing process comprises three main phases:

First Phase (from 2018): The total amount is USD 41.18 million provided as a grant. Of this amount, USD 4.62 million represents the contribution of the Government of the Republic of Tajikistan.

Additional Financing Phase (from 2022): To scale up activities, USD 38 million was allocated as a grant, of which USD 4.63 million is the contribution of the Government of the Republic of Tajikistan.

The third funding stage is scheduled for 2027. Work is currently underway to prepare the project's feasibility study.

2. Technical and Infrastructure Outcomes. The allocated funds are directed primarily toward the modernization of Dushanbe's infrastructure, specifically in the Shohmansur district and other parts of the capital. The following works are being executed within the framework of the project:

  • Sewerage System: Reconstruction of the Southeastern Sewerage Collector and laying of over 110 km of sewerage lines in the Zebunisso and Karotegin mahallas of the Shohmansur district.
  • Water Supply Networks: Construction of over 400 km of trunk and internal water supply lines across the territory of the Shohmansur district.
  • Hydraulic Structures: Construction and rehabilitation of reservoirs with a total capacity of 9,500 cubic meters, construction of one second-lift pumping station, and rehabilitation of 27 vertical wells at the KAF-1 and KAF-2 pumping station sites.
  • Technical Equipment: Procurement and installation of 35 modern second- and third-lift pumping units, as well as over 7,900 water meters for subscribers.
  • Social Aspects: The project includes the construction of the Women's Development Centre building, which contributes to enhancing the role of women in society. The implementation of these measures will bring the quality of water supply and sanitation services in Dushanbe into compliance with modern standards.

  • "Dushanbe Water Supply and Sanitation Project"
    Asian Development Bank
    ОСВ/CW/AF-05
    Design and construction of the Women’s Development Center

    Contract with the joint companies LLC “Stroy Center” and LLC “GM & Partner” dated July 3, 2023, in the amount of USD 1,632.0 thousand was signed, and taking into account the advance payment, USD 1,468.74 thousand was transferred to the company’s account. Construction works at this facility have been fully completed. In accordance with the relevant decision of the Chairman of the city of Dushanbe approving the act of the State Acceptance Commission, the facility is to be transferred to the balance of the State Unitary Enterprise “Dushanbevodokanal”

    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    OCB/CW/AF-04 LOT-2
    Rehabilitation of the sewerage networks of the “Zebunisso” district

    Contract with the joint companies JSC “TajikSGEM,” LLC “AZ Composite” (Azerbaijan), and LLC “Stroy Center” dated December 5, 2022, in the amount of USD 5,632.35 thousand was signed. The funds were fully utilized, taking into account the advance payment, with USD 5,632.35 thousand transferred to the company’s account. Construction works at this facility have been fully completed. Based on the decision of the Chairman of the city of Dushanbe, the facility has been transferred to the balance of the State Unitary Enterprise “Dushanbevodokanal”

    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    ОСВ/CW/AF-04 LOT-1
    Rehabilitation of the sewerage networks of the “Karotegin” district

    Contract with the joint companies JSC “TajikSGEM,” LLC “AZ Composite” (Azerbaijan), and LLC “Stroy Center” dated December 5, 2022, in the amount of USD 4,439.55 thousand was signed. The funds were fully utilized, taking into account the advance payment, with USD 4,439.55 thousand transferred to the company’s account. Construction works at this facility have been fully completed. Based on the decision of the Chairman of the city of Dushanbe, the facility has been transferred to the balance of the State Unitary Enterprise “Dushanbevodokanal.”

    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    ОСВ/CW/AF-03 LOT-3
    Rehabilitation of the Southern Sewer Collector. Contract with JSC “TajikSGEM”

    Dated July 29, 2025, in the amount of USD 3,092.13 thousand was signed, and an advance payment of USD 1,781.22 thousand was transferred to the company’s account. At present, construction works at the facility include trench excavation for laying sewer pipes with diameters of D 1000 mm and D 1200 mm, with a total of 2,730 meters of pipes already installed.

    IN PROGRESS
    FINANCIAL PROGRESS
    90%
    PHYSICAL PROGRESS
    100%
    ОСВ/CW/AF-02 LOT-3

    Rehabilitation of the second‑ and third‑stage networks and establishment of district metering zones: C‑11, C‑17, A‑12, A‑13, and A‑10‑1

    Contract with LLC “TajikSGEM” dated March 4, 2024, in the amount of USD 3298.2 thousand was signed, and taking into account the advance payment, USD 3298.2 thousand was transferred to the company’s account. Construction works at this facility have been fully completed. At present, the acceptance act of the working commission has been signed and submitted to the executive authorities of the city of Dushanbe for the establishment of the State Commission.

    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    ОСВ/CW/AF-02 LOT-2

    Rehabilitation of the second‑ and third‑stage networks and establishment of district metering zones: A‑5, A‑8, A‑10, and C‑9

    Contract with LLC “Stroy Center” dated March 4, 2024, in the amount of USD 2,584.6 thousand was signed, and taking into account the advance payment, USD 2325,8 thousand was transferred to the company’s account. Construction works at this facility have been fully completed. At present, the acceptance act of the working commission has been signed and submitted to the executive authorities of the city of Dushanbe for the establishment of the State Commission.

    IN PROGRESS
    FINANCIAL PROGRESS
    90%
    PHYSICAL PROGRESS
    100%
    ОСВ/CW/AF-02 LOT-1

    Rehabilitation of the second‑ and third‑stage networks and establishment of district metering zones in sub‑areas A‑6, A‑7, and Gastello Street.

    Contract with LLC “Hamsafar” dated March 4, 2024, in the amount of USD 2,229.94 thousand was signed, and taking into account the advance payment, USD 2225,9 thousand was transferred to the company’s account. Construction works at this facility have been fully completed. At present, the facility is under inspection and acceptance by the State Commission.

    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    ОСВ/CW/AF-01 LOT-4

    Construction of a pressure pipeline from Pumping Station No. 192 to the new reservoirs of Quarter 9 and further to the “Zebunisso” reservoirs. Construction of new reservoirs with a capacity of 2×2000 m³ in Quarter 9 of the “Khovaron” neighborhood. Rehabilitation of the third‑stage pumping station of neighborhood No. 192.

     

    Contract with LLC JV “Ittihod Inshoot va Zumrut” dated September 11, 2024, in the amount of USD 2,657.61 thousand was signed, and an advance payment of USD 2391,8 thousand was transferred to the company’s account. At present, works at the facility include completion of concreting of reservoir walls, commencement of installation of reservoir roof formworks, as well as ongoing works on laying and facing of the perimeter wall made of cement blocks.

    IN PROGRESS
    FINANCIAL PROGRESS
    95%
    PHYSICAL PROGRESS
    93%
    ОСВ/CW/AF-01 LOT-3

    Reconstruction of the “Academics” reservoirs, water supply pipelines from Pumping Station No. 192 to the existing reservoirs with a capacity of 2×2000 m³, as well as rehabilitation of the third water pumping station.

    Contract with the Joint Company “Tajikhydroelectromontazh” dated September 11, 2024, in the amount of USD 4,607.00 thousand was signed, and taking into account the advance payment, USD 4146,3 thousand was transferred to the company’s account. At present, works are ongoing at the facility, including installation of pumps in the buildings of the third stage pumping stations of neighborhoods No. 191 and No. 193, “Small Qarotegin,” “Kamola,” and “Bahori,” as well as construction of a perimeter wall made of cement blocks and landscaping at the “Academy of Sciences” reservoirs with a capacity of 2×750 m³.

    IN PROGRESS
    FINANCIAL PROGRESS
    90%
    PHYSICAL PROGRESS
    100%

    WORLD BANK COOPERATION WITH SUE “DUSHANBEVODOKANAL”

    1. General information and implementation stages. In order to improve the reliability of water supply and wastewater services in selected north western parts of Sino district of Dushanbe city and to enhance the operational and economic activities of SUE “Dushanbevodokanal” (Implementing Agency), since 2020 up to the present the “Dushanbe Water Supply and Wastewater Project” has been implemented in accordance with the grant agreement between the Government of the Republic of Tajikistan and the International Development Association (IDA)/World Bank.

    2. Project implementation period:

    Начало: 10 апреля 2020 года

    Completion: December 31, 2024

    Extension for use of saved funds: June 30, 2026

    3. Main directions of the Dushanbe Water Supply and Wastewater Project:

    — Институциональное развитие – 5,5 млн долларов.США

    — Улучшение системы водоснабжения и водоотведения – 25,65 млн долларов США

    — Поддержка реализации Проекта – 0,85 млн. долларов США

    Total: USD 32.0 million

    Out of the total amount, USD 2.0 million is the contribution of the Government of the Republic of Tajikistan.

    4. Technical and infrastructure results. The allocated funds were mainly directed to modernization of Dushanbe city infrastructure, particularly in Sino district. Within the framework of the project, the following activities and works were carried out:

    Система канализации: Замена и прокладка более 27 км канализационных линий в маҳаллях района Сино.
    Система водоснабжения: Замена и прокладка более 72 км магистральных и внутренних линий водоснабжения на территории района Сино.
    Гидротехнические сооружения: Строительство 2 резервуаров воды общей емкостью 12000 кубических метров, строительство 4 станций подкачек третьего подъема на территории насосных станций района Сино.
    Техническое оснащение: Закупка и установка электросберегающего оборудования на 36 насосных станциях третьего подъема; закупка и установка 16 единиц ультразвуковых расходомеров на магистральных трубопроводах; закупка и установка 40 000 штук механических и 12000 штук современных ультразвуковых счетчиков воды для абонентов; приобретение и установка 40 единиц насосного оборудования на 24 насосных станциях подкачек третьего подъема; приобретение 11 единиц коммунальной техники и оборудования для устранения аварий (экскаватор, самосвал, автомашина для передвижной лаборатории и определения утечек воды в сети, инструменты и малое механическое оборудование); 5 единиц серверов различной мощности для укрепления работы биллинговой системы и программы 1С бухгалтерия, закупка и установка нового программного обеспечения для обновления биллинговой системы предприятия.
    Implementation of these measures will ensure improved quality of water supply and wastewater services in Dushanbe city, in line with modern requirements.

    Dushanbe Water Supply and Wastewater Project.
    World Bank
    DWSWP-G-RFQ-10 & DWSWP-G-RFQ-11
    Procurement of equipment and mechanisms for emergency service
    Контракты заключены с ООО “Пулоди Асл” на общую сумму 291,63 тыс. долларов США. Подрядчик осуществил поставку техники и механизмов на таможенную границу РТ, после оформления таможенных процедур, техника полностью была ввезена и сдана на склад ГУП “Душанбеводоканал” для дальнейшего использования. Контракт завершен, стоимость контрактов полностью перечислена на расчетный счет Подрядчика.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-06
    Приобретение ультразвуковых счетчиков воды с модулем автоматического считывания показаний в количестве 3000 штук
    The contract was signed with JV LLC “Imod Dushanbe” and OJSC “TajikSGEM” for the procurement of 3,000 meters in the amount of USD 321.3 thousand. The Contractor fully delivered and handed over the equipment to the warehouse of SUE “Dushanbevodokanal.” The contract has been completed, and the full amount has been paid.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-08
    Procurement and installation of servers for integration of the billing system with 1C Accounting software
    The contract was signed with LLC “Atlas Technology” for the supply and installation of 2 server units. The equipment was delivered to the warehouse and installed. The contract has been completed, and the full amount has been transferred to the Contractor’s bank account.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-07
    Procurement and installation of ultrasonic flow meters on main water supply pipelines
    Контракт заключен с ООО “Рушди Замон” на приобретение и установку ультразвуковых расходомеров в количестве 16 штук на сумму 243,3 тыс. долларов США. Подрядчик осуществил поставку оборудования 25 февраля 2026 года на склад ГУП “Душанбеводоканал”. Работы по установке на улицах Шерализода, И.Сомони, С.Шерози, А.Сино, Маяковского зевершены.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-09
    Приобретение и установка насосного оборудования для насосных станций подкачек 2 и 3-го подъема
    Контракт заключен с ООО “Ориён Чамъ” на сумму 461,38 тыс. долларов США на приобретение и установку 39 единиц насосов. Подрядчик осуществил полную поставку оборудования на территорию страны 24 марта 2026 года. Всего установлено и сдано в эксплуатацию 39 насосного оборудования на станциях 2 –го подъема в количестве 2 единиц и на станциях 3-го подъема – 25 единиц, Зона охвата: улицы Махмадиева, Зарафшон, Шерализода, Гафурова, Сомони, Хувайдуллоева, Маяковского, А.Сино. Контракт завершен, стоимость контракта полностью зачислена на расчетный счет Подрядчика.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/DS-G-05
    Procurement and installation of automatic data reading module for previously installed household mechanical meters
    The contract was signed with JV LLC “Tajikelektrokomplekt” and Baylan Ulcu Aletleri Sanayi Ve Ticaret on October 8, 2025, in the amount of USD 548.83 thousand. The Contractor delivered the equipment to the warehouse of SUE “Dushanbevodokanal” on February 27, 2026. During March–April, 6,300 automatic data reading modules were installed on previously installed mechanical water meters in residential quarters of Sino district. The contract has been completed, and the full amount has been transferred to the Contractor’s bank account.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-16 & DWSWP/G-17
    Procurement of equipment and mechanisms for emergency service
    The contract was signed with LLC “Kangurt‑2” in the amount of USD 243.15 thousand. The equipment and mechanisms were delivered to the warehouse and accepted into the balance of SUE “Dushanbevodokanal.”
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-03
    Procurement of 2 vehicles for mobile laboratory, network leakage detection, equipment and inventory
    The contract was signed with JV “Ittihod Inshoot va Zumrut” in the amount of USD 585.0 thousand. The equipment and machinery were fully delivered and, according to the acceptance act dated December 12, 2024, handed over to the warehouse of SUE “Dushanbevodokanal.”
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    DWSWP/G-01
    Procurement of 40,000 water meters
    The contract was signed with JV LLC “Tajikelektrokomplekt” and Baylan Ulcu Aletleri Sanayi Ve Ticaret in the amount of USD 1,208.40 thousand. The contract was completed ahead of schedule, and the Contractor has been fully paid.
    Completed
    FINANCIAL PROGRESS
    100%
    PHYSICAL PROGRESS
    100%
    INSTITUTIONAL REPORTS
    2022
    Данные не найдены
    2023
    Данные не найдены
    2024
    Данные не найдены
    2025
    Данные не найдены
    2026
    Данные не найдены
    SOCIAL MONITORING REPORTS
    2022
    Данные не найдены
    2023
    Данные не найдены
    2024
    Данные не найдены
    2025
    Данные не найдены
    2026
    Данные не найдены
    ENVIRONMENTAL MONITORING REPORTS
    2022
    Данные не найдены
    2023
    Данные не найдены
    2024
    Данные не найдены
    2025
    Данные не найдены
    2026
    Данные не найдены
    Key Indicators
    Completed Projects
    0 +
    facilities under construction
    0 +
    residents gained access
    0 К+
    environmental projects
    0 +