COOPERATION BETWEEN SUE "DUSHANBEVODOKANAL" AND INTERNATIONAL PARTNERS

SUE "Dushanbevodokanal" (DVK) is carrying out a large-scale and consistent modernization of the entire water supply and sanitation system of the capital of the Republic of Tajikistan. This work is conducted as part of the implementation of state programs and relies on a long-term strategic partnership with leading international financial institutions.

Cooperation with key international donors—the Asian Development Bank (ADB) and the World Bank (WB)—has today moved far beyond the traditional attraction of investment loans and grants. It represents a comprehensive, deeply integrated program of institutional and technical transformation for the entire urban water sector. Joint projects are aimed at adapting the city’s life-support systems to high rates of urbanization and the challenges of climate change.

Currently, multi-vector cooperation with international partners is being successfully implemented across three strategic areas:

1. Infrastructure Modernization and Environmental Safety Assurance
Investment infusions from international donors are aimed at the capital renewal and expansion of the enterprise's physical assets, which makes it possible to dramatically increase the reliability of urban infrastructure.

1.1. Reconstruction of Headworks: Projects include the deep modernization of water treatment plants (WTP), first and second-lift pumping stations, and the introduction of modern, safe drinking water disinfection technologies.

1.2. Restoration and Expansion of Networks: Large-scale work is underway to replace worn-out main water pipelines and reconstruct gravity and pressure sewage collectors, which minimizes the risks of accidents and improves the sanitary and ecological situation in the city.

1.3. Loss Management and Network Zoning: A crucial practical step is the division of the urban network into isolated District Metered Areas (DMAs). This allows for continuous monitoring of supply volumes, effective management of hydraulic pressure, and systematic reduction of commercial and technical losses (non-revenue water).

2. Digital Transformation, Automation, and Customer Service Optimization.
Modern management standards require a transition to digital technologies. Joint projects with the ADB and the World Bank provide for end-to-end automation of all production and sales chains of SUE "DVK."

2.1. Introduction of SCADA Systems: A unified intelligent Supervisory Control and Data Acquisition (SCADA) system is being created, which allows for real-time monitoring of pumping unit operations, reservoirs, and key metering nodes.

2.2. Development of Commercial Metering: A phased transition to "smart" water meters (smart meters) with remote reading transmission capabilities is being implemented, ensuring absolute transparency in calculations with consumers.

2.3. Modernization of IT Infrastructure and Call Center: A complete transformation of the enterprise's contact center is underway, shifting from manual processes to modern digital platforms. The integration of the Call Center with Geographic Information Systems (GIS) and the updated billing system allows for prompt responses to citizen requests, reducing the time required to resolve emergency situations.

3. Institutional Development, Corporate Governance, and Gender Equality.
The sustainability of technical achievements is impossible without the modernization of management approaches. Within the framework of assistance programs, special attention is paid to strengthening the institution of SUE "Dushanbevodokanal" itself as a financially stable enterprise.

3.1. Results-Based Management: International corporate governance standards are being introduced at the enterprise, including a clear system of Key Performance Indicators (KPIs) and the use of Performance-Based Contracts in operational activities.

3.2. Capacity and Expertise Building: Advanced training programs are regularly conducted for engineering, technical, and administrative personnel, including the organization of international study tours to exchange experience with advanced water utilities in foreign countries.

3.3. Implementation of Gender Policy and Inclusivity: One of the priority vectors of cooperation is overcoming gender stereotypes in the municipal sector. Programs to support women's leadership are being developed and implemented, creating equal conditions for the professional and career growth of female specialists in the engineering, IT, and management spheres of DVK.

Main Strategic Goal of the Partnership

The accumulation of advanced international experience and investment is aimed at creating a financially sustainable, high-tech, environmentally responsible, and customer-oriented utility enterprise. SUE "Dushanbevodokanal" strives to guarantee uninterrupted, safe, and economically affordable water supply and sanitation for every resident, state institution, and commercial enterprise of the dynamically developing capital.

WORLD BANK COOPERATION WITH SUE “DUSHANBEVODOKANAL”

 

1. General information and implementation stages. In order to improve the reliability of water supply and wastewater services in selected north western parts of Sino district of Dushanbe city and to enhance the operational and economic activities of SUE “Dushanbevodokanal” (Implementing Agency), since 2020 up to the present the “Dushanbe Water Supply and Wastewater Project” has been implemented in accordance with the grant agreement between the Government of the Republic of Tajikistan and the International Development Association (IDA)/World Bank.

2. Project implementation period:

Start: April 10, 2020

Completion: December 31, 2024

Extension for use of saved funds: June 30, 2026

3. Main directions of the Dushanbe Water Supply and Wastewater Project:

— Institutional development – USD 5.5 million     

— Improvement of water supply and wastewater system – USD 25.65 million                                                                                                                          

— Project implementation support – USD 0.85 million

Total: USD 32.0 million

Out of the total amount, USD 2.0 million is the contribution of the Government of the Republic of Tajikistan.

4. Technical and infrastructure results. The allocated funds were mainly directed to modernization of Dushanbe city infrastructure, particularly in Sino district. Within the framework of the project, the following activities and works were carried out:

  • Wastewater system: Replacement and installation of more than 27 km of sewerage lines in mahallas of Sino district.
  • Water supply system: Replacement and installation of more than 72 km of trunk and internal water supply lines in the territory of Sino district.
  • Hydraulic structures: Construction of 2 water reservoirs with a total capacity of 12,000 cubic meters; construction of 4 booster pump stations of the third lift in the territory of Sino district pumping stations.
  • Technical equipment: Procurement and installation of energy saving equipment at 36 third lift pumping stations; procurement and installation of 16 ultrasonic flow meters on trunk pipelines; procurement and installation of 40,000 mechanical and 12,000 modern ultrasonic water meters for subscribers; procurement and installation of 40 pumping units at 24 booster pump stations of the third lift; procurement of 11 units of municipal machinery and equipment for emergency response (excavator, dump truck, vehicle for mobile laboratory and detection of water leaks in the network, tools and small mechanical equipment); 5 servers of different capacities to strengthen the operation of the billing system and 1C accounting program; procurement and installation of new software to update the enterprise’s billing system.

Implementation of these measures will ensure improved quality of water supply and wastewater services in Dushanbe city, in line with modern requirements.

Dushanbe Water Supply and Wastewater Project.
World Bank
DWSWP-G-RFQ-10 & DWSWP-G-RFQ-11
Procurement of equipment and mechanisms for emergency service
Контракты заключены с ООО “Пулоди Асл” на общую сумму 291,63 тыс. долларов США. Подрядчик осуществил поставку техники и механизмов на таможенную границу РТ, после оформления таможенных процедур, техника полностью была ввезена и сдана на склад ГУП “Душанбеводоканал” для дальнейшего использования. Контракт завершен, стоимость контрактов полностью перечислена на расчетный счет Подрядчика.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-06
Приобретение ультразвуковых счетчиков воды с модулем автоматического считывания показаний в количестве 3000 штук
The contract was signed with JV LLC “Imod Dushanbe” and OJSC “TajikSGEM” for the procurement of 3,000 meters in the amount of USD 321.3 thousand. The Contractor fully delivered and handed over the equipment to the warehouse of SUE “Dushanbevodokanal.” The contract has been completed, and the full amount has been paid.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-08
Procurement and installation of servers for integration of the billing system with 1C Accounting software
The contract was signed with LLC “Atlas Technology” for the supply and installation of 2 server units. The equipment was delivered to the warehouse and installed. The contract has been completed, and the full amount has been transferred to the Contractor’s bank account.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-07
Procurement and installation of ultrasonic flow meters on main water supply pipelines
Контракт заключен с ООО “Рушди Замон” на приобретение и установку ультразвуковых расходомеров в количестве 16 штук на сумму 243,3 тыс. долларов США. Подрядчик осуществил поставку оборудования 25 февраля 2026 года на склад ГУП “Душанбеводоканал”. Работы по установке на улицах Шерализода, И.Сомони, С.Шерози, А.Сино, Маяковского зевершены.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-09
Приобретение и установка насосного оборудования для насосных станций подкачек 2 и 3-го подъема
Контракт заключен с ООО “Ориён Чамъ” на сумму 461,38 тыс. долларов США на приобретение и установку 39 единиц насосов. Подрядчик осуществил полную поставку оборудования на территорию страны 24 марта 2026 года. Всего установлено и сдано в эксплуатацию 39 насосного оборудования на станциях 2 –го подъема в количестве 2 единиц и на станциях 3-го подъема – 25 единиц, Зона охвата: улицы Махмадиева, Зарафшон, Шерализода, Гафурова, Сомони, Хувайдуллоева, Маяковского, А.Сино. Контракт завершен, стоимость контракта полностью зачислена на расчетный счет Подрядчика.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/DS-G-05
Procurement and installation of automatic data reading module for previously installed household mechanical meters
The contract was signed with JV LLC “Tajikelektrokomplekt” and Baylan Ulcu Aletleri Sanayi Ve Ticaret on October 8, 2025, in the amount of USD 548.83 thousand. The Contractor delivered the equipment to the warehouse of SUE “Dushanbevodokanal” on February 27, 2026. During March–April, 6,300 automatic data reading modules were installed on previously installed mechanical water meters in residential quarters of Sino district. The contract has been completed, and the full amount has been transferred to the Contractor’s bank account.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-16 & DWSWP/G-17
Procurement of equipment and mechanisms for emergency service
The contract was signed with LLC “Kangurt‑2” in the amount of USD 243.15 thousand. The equipment and mechanisms were delivered to the warehouse and accepted into the balance of SUE “Dushanbevodokanal.”
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-03
Procurement of 2 vehicles for mobile laboratory, network leakage detection, equipment and inventory
The contract was signed with JV “Ittihod Inshoot va Zumrut” in the amount of USD 585.0 thousand. The equipment and machinery were fully delivered and, according to the acceptance act dated December 12, 2024, handed over to the warehouse of SUE “Dushanbevodokanal.”
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
DWSWP/G-01
Procurement of 40,000 water meters
The contract was signed with JV LLC “Tajikelektrokomplekt” and Baylan Ulcu Aletleri Sanayi Ve Ticaret in the amount of USD 1,208.40 thousand. The contract was completed ahead of schedule, and the Contractor has been fully paid.
Completed
FINANCIAL PROGRESS
100%
PHYSICAL PROGRESS
100%
INSTITUTIONAL REPORTS
2022
Данные не найдены
2023
Данные не найдены
2024
Данные не найдены
2025
Данные не найдены
2026
Данные не найдены
SOCIAL MONITORING REPORTS
2022
Данные не найдены
2023
Данные не найдены
2024
Данные не найдены
2025
Данные не найдены
2026
Данные не найдены
ENVIRONMENTAL MONITORING REPORTS
2022
Данные не найдены
2023
Данные не найдены
2024
Данные не найдены
2025
Данные не найдены
2026
Данные не найдены